Phoenix Project

Final Environmental Impact Statement

USDI Bureau of Land Management

 

 

Technical Comments by

James R. Kuipers, P.E.

Center for Science in Public Participation

 

 

On behalf of

Great Basin Mine Watch

Reno, NV

 

February 7, 2002

 

 

1.0       Introduction

 

The following comments on the Phoenix Project Final Environmental Impact Statement (FEIS)[1] have been prepared on behalf of Great Basin Mine Watch.  The comments are based on review of the FEIS and supporting documents as referenced, and extensive professional expertise in the field of reclamation and closure planning and operations, and financial assurance determination.  The author is familiar with the Phoenix Project site and in particular with their groundwater contamination issues, having performed wastewater treatment engineering evaluation services in the past to address groundwater contamination issues at the site.

 

The Phoenix Project is a proposed mining operation located approximately 12 miles southwest of Battle Mountain, in Lander County, Nevada.  The project is an expansion of current mining operations being proposed by Battle Mountain Gold Company, a wholly owned subsidiary of Newmont Mining Corporation.  The proposed operation would consist of open pit mining, cyanide heap leaching of low-grade ore, and cyanide mill leaching of higher-grade ore, with waste rock and tailings disposal areas.  The proposed expansion would result in approximately 4,295 acres of new disturbance on public and private lands in the project area.

 

These comments are organized to address reclamation and closure planning, and also to address the determination of financial assurance.  The comments reference information from other similar sites where the BLM and/or other state and federal agencies have addressed similar circumstances and have established accepted means to address the issues at the Phoenix Project.  Specific examples of reclamation and closure information and financial assurance calculations that are referenced have been attached in an Appendix to these comments.

 

2.0       Reclamation and Closure

 

Experience in successful treatment of reclamation and closure issues at other sites has shown that several key issues must be addressed, including: the characterization of waste rock materials; surface water and ground water impacts; and revegetation.  Other key issues such as geotechnical stability may be important at some sites.

 

Review of the Phoenix Project FEIS shows that in particular the related issues of historic mining impacts to groundwater, waste rock and tailings characterization, future impacts to surface water and ground water, and revegetation, are key to determining an effective reclamation and closure strategy at the site.  As an example, the following site-specific features are noted:

 

  • According to the FEIS (p. 3.2-33), overall, the highest total dissolved solids concentrations occur in ground water samples from areas near the Gold Tailings Facility and the Copper Leach Waste Area.  Specific ground water monitoring and/or mitigation requirements are applicable to both of these areas pursuant to the Battle Mountain Complex Water Pollution Control Permit.

 

  • According to the FEIS (p. 3.2-34,35), based on a cutoff acid-neutralizing potential to acid-generating potential ratio of 3.0 recommended by the BLM, these results indicate that the majority of the rocks in the pit wall surfaces and waste rock have the potential to generate acid, and (p. 3.2-36) the results of the kinetic tests indicate that most of the rocks in the project area directly associated with mining operations (pits and waste rock) have the potential to generate acid rock drainage.  This finding is consistent with the observation that surface water and some groundwater in the vicinity of the existing pits are acidic and have elevated concentrations of sulfate and metals.

 

  • According to the FEIS (p. 2-48), BMG has developed a contingent long-term management plan to address potential ground water impacts associated with the proposed Phoenix Project waste rock facilities.

 

The FEIS does not contain crucial information on tailings or heap leach material characterization, or specific information as part of the plan on how the existing ground water contamination from past mining operations will be addressed.

 

As evidenced by nearly all reclamation and closure plans where acid generation has been recognized and dealt with, the following key features are common to those plans:

 

1.                  Capture and treatment of existing surface water and ground water contamination.

2.                  Source reduction by sloping, capping and revegetation of waste rock and tailings facilities typically utilizing engineered water barrier or water balance covers augmented by surface water controls.

3.                  Provisions for capture and treatment of future surface water and ground water contamination.

 

The impact of acid drainage and appropriate mitigation measures has been established by BLM and other state and federal agencies where this proven and all to common phenomena has been recognized, such as throughout the states of Montana and New Mexico, as well as some specific sites in other locations such as Summitville in Colorado, Iron Mountain in California, and at the Brohm mining operations in South Dakota, to name a few.  Because of the particular severity and expense of the reclamation and closure tasks associated with acid drainage many of these sites have also fallen under Environmental Protection Agency (EPA) Superfund regulation, including several existing mine sites with characteristics similar to those of the Phoenix Project. 

 

It is significant that up to the present time acid drainage has literally not been recognized or accounted for in reclamation and closure planning by the responsible state and federal regulatory agencies in Nevada.  The enormity of affect that acid drainage has caused to planning and financial assurance determinations an other states demonstrates the significance of the need for the state and federal agencies to recognize and address this matter at the Phoenix Project and other mine sites in Nevada and other states where the responsible agencies have failed to carry out their responsibility in this regard.  It is likely that the situation at the Yerington copper mine, which is being considered as a Superfund site, and where the responsible company has declared bankruptcy, will provide the State of Nevada with some experience in developing the necessary tasks and financial assurance so as to not end up with similar experiences at the Phoenix Project and other sites with similar potential for both significant environmental impacts and for under-funded financial assurance.

 

The BLM in particular has experience at two sites in Montana which bear close similarities to the Phoenix Project: the Zortman and Landusky mines; and the Golden Sunlight mine.  Similar to the Phoenix Project, both are large gold mines where acid drainage is present and are situated in comparably semi-arid climates.  However, the plans for addressing the existing and future reclamation and closure needs, and for financial assurance, have been dealt with in a much more conservative and responsible manner than is proposed for the Phoenix Project in the FEIS. 

 

The following comments are provided relevant to specific aspects of the reclamation and closure plan as described in the FEIS.

 

 

 

2.1       Revegetation Guidelines

 

The FEIS (p. 2-37) states that to complement and support reclamation/revegetation efforts and to promote reclamation development, a reclamation monitoring program including revegetation test plots would be developed for the proposed Phoenix Project.  This program would be targeted to examine, review, and determine concurrent reclamation practices, cultural treatments, and techniques to promote successful site reclamation.

 

Although mining has been ongoing at the site during the past 20+ years, including for over 10+ years during which the Nevada Department of Environmental Protection (NDEP) and the BLM have required reclamation and closure planning, it is disheartening to see that little or no previous reclamation has been performed which can contribute to determining reclamation needs.  Basic requirements such as revegetation test plots to determine how best to achieve effective reclamation are only now being recognized and required.  As has been repeatedly demonstrated at other sites, a conceptual reclamation revegetation plan such as contained in the Phoenix Project FEIS, without empirical field data to lend support to its assumptions, is rarely if ever successful.  This is particularly true where the techniques relied upon must deal with site-specific conditions such as unfavorable geochemistry, lack of sufficient suitable growth media, and semi-arid climatic conditions.  This is all the more critical because a successful revegetation result is heavily depended upon to control infiltration and reduce acid generation at the Phoenix Project. 

 

The revegetation plan associated with the proposed action in the FEIS represents a minimal approach.  The standard and accepted approach to existing and future impacts associated with acid drainage from the different mine areas requires that revegetation succeed in order to reduce infiltration of meteoric water, as well as in order to prevent erosion and maintain the cover characteristics, and to ensure suitable post-mining land use.

 

The plan should be modified to recognize the following requirements:  At least 18 inches of suitable growth medium (salvaged topsoil to the greatest extent possible), including having the desired texture (density, coarse fragments and clay contents), organic matter, moisture retention, fertility, and pH characteristics adequate to propagate sustainable vegetation.  Other re-vegetation factors that also must be assessed include re-vegetation through time, slope and aspect, competition, weedy species and undesirable invader plants, and plant cover.  All these aspects should be included in the design and monitoring plan for the revegetation test plots and additional variables such as alternative cover designs and thickness, materials of construction, and revegetation approaches should also be evaluated.

 

The underlying assumption of the cost estimate for revegetation should consider the likelihood that successful revegetation will require a sustained rather than one time effort as depicted in the reclamation plan.  Experience has shown that multiple plantings of at least some areas is to be expected due to climatic, insect and other factors, and that fertilization over an extended time period is typically necessary, particularly where mined rock is to be substituted for a more suitable growth medium.

 

2.2       Open Pits and Waste Rock Reclamation

 

According to the FEIS (p. 2-41, 42), a large portion of the waste rock generated by the Phoenix Project would be used to backfill the Phoenix, Midas, Iron Canyon, Reona, and Minnie pits.  Submerging waste rock in pit backfill facilities below the post mining water table is intended to eliminate contact with atmospheric oxygen and limit the potential for producing acidic solutions.  Capping material would be placed as a nominal 5-foot cap over the final contoured surface areas…to promote revegetation and evapotranspiration of precipitation of both the waste rock facilities and the pits backfilled with waste rock.

 

The need to eliminate infiltration into the acid-generating waste rock dumps, leach piles and tailing facilities, as well as the backfilled open pit, along with the type of vegetative treatment planned for reclamation, should dictate soil replacement depth.  In order to reduce infiltration to the greatest extent practical, a water balance cover (in which plants transpire water and the soil prevents water infiltration to underlying mine waste), or a water barrier cover (in which an impermeable water barrier to prevent water infiltration) should be specified for all potentially acid-generating areas.  The engineered cap should be designed so as to optimize desirable characteristics and achieve minimize infiltration to underlying acid generating waste while maximizing revegetation so as to increase evapotranspiration.

 

The FEIS did not adequately evaluate the trade-offs of pit backfilling.  While in general backfilling is recommended in order to affect more complete reclamation of the disturbed surface areas, where acid drainage generation characteristics are present an examination of water quality and other issues related to the backfill is typically considered necessary.  In fact, this approach is typically taken at sites comparable to the Phoenix Project to justify not backfilling, which is contrary to the approach being advocated in the FEIS.  Of particular concern is the inundation of backfilled materials by rebounding groundwater.  While the proposal to amend backfilled materials below the water table recognizes their acid drainage generating potential, it is illogical.  The material being stored above the water table has the greatest potential to be further oxidized and therefore should similarly be amended while being placed (this would apply to waste rock dumps, tailings and heap leach materials as well), whereas the submerged materials would be stored in a reducing atmosphere and be less subject to oxidation (therefore not requiring amendment).  In addition, the amendment of the backfilled waste with alkaline modifiers such as lime will result in greater solubility of metalloids such as arsenic and selenium, and could lead to additional ground water contamination concerns.

 

The proposal to backfill should be evaluated from the standpoint of technical, environmental, cost and aesthetic trade-offs.  A process like a multiple accounts analysis or similar means of conducting a science based technical evaluation that ranks and weights the various pros and cons of pit backfill is recommended to ensure that the proposal is logical and will not result in undue degradation to ground water and other resources.

 

2.3       Tailings Facilities Reclamation

 

According to the FEIS (p. 2-43), once tailings facilities have been reshaped into the desired configurations, a minimum of 2-foot thickness of capping material would be placed to promote revegetation and evapotranspiration of precipitation and to minimize infiltration of meteoric water. 

 

According to the FEIS (p. 2-43), a number of options are available for managing fluid that may continue to drain from the tailings facilities after reclamation is conducted.  The FEIS does not contain a geochemical characterization of the tailing materials; however it should be assumed that if the waste rock is acid generating, the ore bearing material, which is typically more mineralized, will have at least equal or greater potential to generate acid drainage.  The FEIS also does not contain information adequate to assess tailings closure requirements from a consolidation standpoint, as well as ultimate transport and fate of fluid from the tailings facilities following closure.  While the tailings facility liner will reduce short-term potential for migration of tailings fluid into ground water, the liner will degrade over time.  Like the existing tailings facilities at the Phoenix Project site, long-term water management consisting of capture and treatment will most likely result from the proposed tailings facilities.

 

The FEIS has not adequately addressed tailings facility fluid management from the existing mine, proposed project, or post-reclamation standpoint, and it has not been recognized in corresponding financial assurance determinations.  The proposed plan should be modified to assume the most likely scenario of fluid management as being active management including capture and treatment due to the acid drainage generating nature of the tailings, the potential cost of which should also be included in the financial assurance determination.

 

2.4       Heap Leach Facility Reclamation

 

According to the FEIS (p. 2-43), at present heap stabilization consists of rinsing the leached ore with neutralized leach solution or fresh water.  The FEIS (p. 2-44) assumes a relatively simple approach that would be considered successful when the pad effluent exhibits the following characteristics:  pH between 6 and 9, WAD cyanide concentrations below 0.2 mg/L, and the concentration for levels for other constituents do not have the potential to degrade the waters of the State.  Also (p. 2-44), 6 inches of cover material would be placed, and the entire heap revegetated.  Management of fluid that might continue to drain from the reclaimed heap would be accomplished using the methodologies … from tailings facilities.

 

As has been shown by Miller and others, heap leach neutralization is often times significantly more difficult than anticipated, and simple approaches such as that suggested in the proposed plan are rarely successful in achieving the desired approach.  This is particularly common where acid generation is likely to result from spent heap leach piles.  Like the tailings material, the heap leach ore is likely to be similarly mineralized as the waste rock, and also be acid generating.  Once the protective alkalinity added during the heap leach process is consumed, it is possible that the heaps themselves will become acidic, resulting in a long-term need for fluid management.  Numerous examples of similar phenomena exist from operating mine sites, including such as is evident and has been extensively evaluated at the Zortman and Landusky mine sites, which have highly similar geochemical properties to the Phoenix Project site. [2]

 

The FEIS has not adequately addressed long-term heap leach fluid management and it has not been recognized in corresponding financial assurance determinations.  The proposed plan should be modified to assume the most likely scenario to fluid management as being active management including capture and treatment due to the acid drainage generating nature of the heap leach materials, the potential cost of which should also be included in the financial assurance determination.

 

2.5       Contingent Long-term Ground Water Management

 

According to the FEIS (p. 2-48), BMG has developed a contingent long-term management plan to address potential ground water impacts associated with the proposed Phoenix Project waste rock facilities.

 

Given the acid drainage generating characteristics of the waste rock, it is nearly certain that the requirement for water management is not properly termed “contingent,” but in fact will be necessary.  For that reason it should be a fully identified and accounted for task in the reclamation and closure planning of the proposed Phoenix Project.

 

The proposed plan does not address acid drainage that will likely result from the tailings facility and heap leach areas, as well as from the open pits and other areas.  It similarly does not address ground water contamination that is presently and in the future will continue to emanate from the existing tailings facilities.  These features make it obvious that there is an immediately existing as well as future need to conduct water management activities at the site that should be included in the reclamation and closure planning.  The requirements in this regard are likely to result in significant financial assurance requirements.

 

 

 

3.0       Financial Assurance

 

Information on financial assurance is contained in the FEIS (p. 2-48) and in a reclamation cost estimate submitted by the project proponent to the BLM.[3] 

 

It is notable that the Bush Administration supported retention of the proposed changes to the 3809 Surface Mining Regulations addressing financial assurance, while rejecting all other proposed changes to the rules.  The issues of environmental pollution caused by hardrock metals mining as well as the recognition of the substantial economic burden that may be imposed on the public have caused bipartisan recognition of the immediate need for a change from past practices and to require adequate financial assurance.  According to the BLM 3809 revised rules BLM has decided that to protect and restore the environment and to limit taxpayer liability, financial guarantees for reclamation should be required at 100 percent of the estimated cost for BLM to have the reclamation work performed.  This includes any costs that may be necessary for long-term water treatment or site care and maintenance.

 

In a previous report I have identified the significance of acid drainage generation with respect to reclamation and closure tasks and their resulting capital and operating costs as they affect financial assurance.[4]  As experience has shown at several mine sites including at the Zortman and Landusky, and Golden Sunlight mines, both of which are regulated by Montana BLM, the presence of acid generation can significantly impact financial assurance requirements.  In many cases this has resulted in an increase of approximately an order of magnitude to pay for surface reclamation and water treatment associated mitigations, and has raised the typical cost of reclamation and closure from an aggregated $5,000 - $15,000 per acre, to in excess of $50,000 to $100,000 or more per acre.

 

The Golden Sunlight Mine in Montana and the Molycorp Questa Mine in New Mexico are examples of where reclamation and closure plans requiring long-term water treatment have been decided and financial assurance established.  The two financial assurance requirements, at approximately $63 million and $152 million respectively, are currently the largest financial assurances at operating mines in the U.S., and are typical of the result of the realization of acid drainage generating characteristics as they affect mine reclamation and closure planning requirements and financial assurance determination.  Additional information on both these mines has been attached.[5]

 

The Zortman-Landusky Mine is another significant case in point with respect to bonding.  Despite the existence of significant bonding of approximately $72 million when its owner Pegasus Gold went bankrupt, the BLM and Montana DEQ have recently identified a need for an additional $33 million to address a shortfall for surface reclamation and water treatment in perpetuity for their preferred alternative.[6]  The primary factors attributable to the financial assurance shortfall were an underestimate of the acid drainage generation at the site and a corresponding need for additional surface reclamation and water treatment capacity and long-term financial assurance.

 

3.1       Reclamation and Closure

 

The FEIS (p. 2-48) provides an estimate for reclamation and fluid management of approximately $32,073,000 for the first 3-year phase of the proposed operation.  The maximum forecasted reclamation cost estimate for the project during any phase is approximately $55,800,000 during years 21-23 of operation. 

 

According to the FEIS (p. 2-48), the bond amount would be adjusted, as necessary, every 3 years to reflect disturbance proposed in the upcoming 3-year phase or if there is an amendment to the plan.

 

Our review of the Phoenix Project financial assurance estimate shows that it has been appropriately performed as a first order engineering cost estimate.  Cost estimates for wages (Davis-Bacon), equipment costs (hourly rental costs from vendors), and adjusted unit costs are consistent with our experience and recommendations and the revised 3809 Surface Mining Regulations (effective January 2001).  We noted the following inconsistencies with recommended practice in the Phoenix Project cost estimate.

 

Direct Costs

 

The direct costs in the reclamation cost estimate are for the proposed plan.  The previous sections comments on reclamation and closure identified deficiencies in the proposed plan with respect to cover design and materials, revegetation, and water treatment for existing as well as future ground water remediation.

 

Based on experience at other sites where reclamation and closure of similar mine sites having acid drainage has taken place, including those cited elsewhere in these comments, direct capital costs for surface reclamation and water management will most likely be higher than estimated for the proposed plan.  Engineered covers designed to minimize infiltration are likely to require either modified or different material characteristics, and it is likely that a more desirable growth medium for revegetation can be located in close proximity to the site.  Adequate revegetation establishment to promote evapotranspiration will likely require more intensive and longer-term effort than suggested by the proposed plan.  Capital requirements for water management including capture, conveyance, storage, treatment and discharge will most likely significantly exceed the estimated requirements in the proposed plan, both in terms of quantity of flow treated as well as load of acid and dissolved contaminants.

 

It is not possible to make an accurate estimate as to the actual required tasks and corresponding costs for reclamation and closure at the Phoenix Project site given the inadequacy of the information in the FEIS.  The FEIS is based upon a largely conceptual reclamation and closure plan that assumes a low to moderate level of activity and cost associated with acid generation.  However, cost estimates for comparable sites that are based on adequate information and identify and address acid generation are more complex in their treatment of the problem and have a significantly higher unit and total cost than in the cost estimate for the proposed plan.  Based on an average total unit cost of $75,000 per acre for reclamation at similar projects (see projects cited elsewhere in these comments and as provided in the Appendix) versus the $14,452 per acre in the cost estimate for the proposed plan, a shortfall of approximately $60,000 per acre or more than $100 million total may exist for the proposed bond amount.

 

The existence of this discrepancy in the financial assurance amount, given the similarity of the Phoenix Project’s characteristics to other mine sites where plans have been established that adequately deal with acid drainage and associated issues, supports the recommendation that a more extensive and immediate assessment of existing contamination and reclamation and closure requirements and associated financial liability be conducted by the responsible agencies, with assistance from the EPA and other knowledgeable agencies.  If any future mining takes place, it should be assessed from the standpoint of potentially aggravating a significant existing problem, and it similarly should be more adequately addressed before approval is given in order to ensure an adequate reclamation and closure plan and financial assurance.

 

Indirect Costs

 

·        Cost Escalation.  The financial assurance estimate provided by the project proponent is based on a lump sum of costs in 2001 dollars.  Actual reclamation would take at least three to five years or more in which event the bond, which would be paid out as reclamation occurs unless otherwise specified, would not keep up with inflation and other factors.  It is standard practice to establish a reclamation schedule (see Golden Sunlight Bond Calculations in Appendix) and include cost escalation in order to determine the NPV of the financial assurance instrument for the year of its establishment.  A correction should be made to account for both escalation since the 2001 cost estimate was performed as well as future cost escalation.  The typical cost escalation factors used are 3.0% per year or as estimated by the Means Heavy Construction Costing Index (approximately 3.3% average per year over last ten years).

 

·        Administrative Costs.  The Office of Surface Mining (OSM) has established long-standing costs associated with administrative overheads of agency operated reclamation and closure activities.  The OSM guidelines identify mobilization and demobilization, contingencies, engineering redesign, contractor profit and overhead, and reclamation management fees as indirect cost categories.[7]  In addition individual states must include applicable insurance, tax and contractor bonding requirements.  The cost estimate for the proposed plan includes mobilization and demobilization at 5%, contingencies at 6%, no allowance for engineering redesign, contractor profit and overhead at 10%, and BLM administration at 10%.  In addition, Insurance (1.5% of labor) and performance and payment bonds (3%) were included.  The contractor overhead and profit should be corrected to 20% to reflect typical costs related to government contracting procedures, and an allowance of at least 5% should be made for engineering redesign.  This would result in an increase in indirect costs of approximately 15% over that contained in the cost estimate for the proposed plan.

 

The three-year financial assurance review needs to do more than adjust for additional area and cost escalation.  It should also be reviewed with respect to potential changes in site aspect or characterization and the reclamation and closure plan modified as necessary to mitigate future occurrences with corresponding changes made to the financial assurance estimate.

 

3.2       Long-term Costs

 

According to the FEIS (p. 2-48), at project startup, BMG would be required to establish a long-term trust fund and provide an interim surety to cover potential costs to implement the Contingent Long-term Groundwater Management Plan.  Initially, the long-term contingency fund would consist of a $1,000,000 interim surety (e.g. performance bond) for up to 20 years following startup of Phoenix Project operations.  The purpose of this interim surety is to ensure that there are sufficient monies to fully fund the self-sustaining trust fund.  The initial interim surety amount is based upon a conservative preliminary engineering cost estimate including future average annual costs of $64,000 per year for monitoring, and average annual costs of $483,000 for mitigation.

 

The assumptions used in the proposed plan assumes short-term and long-term water management requirements for up to and beyond 130 years and greater than 1000 years, but in all cases requiring eventual groundwater capture and treatment at some point in the future for an extended period of time.  However, it would be erroneous to base the actual long-term water management costs on the estimates contained in the FEIS as it also states (p. 3.2-55) it is important to note that there is considerable uncertainty associated with long-term predictions of potential impacts to ground water quality resulting from infiltration through the waste rock facilities.

 

This matter has been dealt with in a consistent matter at other sites in other states, including those where BLM was responsible, by requiring the financial assurance estimate to assume that all existing and eventual water treatment facilities were available either during or immediately post-mining and reclamation.  This is reflected in the cost estimates for the Golden Sunlight Mine and Molycorp Questa Mine reclamation and closure plans (see Appendix).

 

Table 1 shows the potential operating costs associated with water management based on the proposed plan and information contained in the FEIS.  That estimate shows that the necessary amount in a trust fund based on a Net Present Value (NPV) established in 2002 for future water management operations would be $9.1M versus the proposed $1.0M financial assurance amount.  The NPV is based on a 3% inflation rate (approximately the average inflation rate over the past 100 years) and a 6% interest rate (assumes trust fund is placed in a moderate to low risk annuity or similar instrument consistent with typical state and federal investment requirements) for a 3% per annum net positive rate.

 

Table 2 shows the likely operating costs if actual site conditions are realized based on the assumption that water treatment requirements will be a factor of four times more onerous (a factor of 2.6 times rather than four times the costs estimated for treatment in the proposed plan was used to reflect the efficiency of scale of a larger plant) and adding in an additional $200,000 per year for site operation and maintenance.  The estimate shows that the necessary amount in a trust fund based on a Net Present Value (NPV) established in 2002 for future water management operations would be $47.3M versus the proposed $1.0M financial assurance amount.  The NPV is based on a 3% inflation rate (approximately the average inflation rate over the past 100 years) and a 6% interest rate (assumes trust fund is placed in a moderate to low risk annuity or similar instrument consistent with typical state and federal investments) for a 3% per annum net positive rate.

 

This information demonstrates the significant shortfall of the proposed long-term financial assurance based on the assumptions of the proposed plan, as well as the even greater shortfall which might occur due to acid drainage characteristics.  These figures highlight the gross inadequacy of the proposed financial assurance amount as well as the factors which have been used to calculate the amount.  It is recommended that the amount of financial assurance in the form a trust fund for water treatment in perpetuity be calculated to include existing and future water treatment needs in the present and assumed to be necessary immediately following mining and reclamation, and that those calculations be based on conservative rather than best case scenarios.

3.0            Conclusions

 

Overall, it is concluded that the proposed plan for the Phoenix Project is significantly inadequate in that it does not propose adequate measures to address acid drainage generating characteristics that otherwise will certainly result in significant degradation of water resources. 

 

The proposed plan significantly underestimates the need for source control measures such as engineered covers and adequate revegetation.  Ground water contamination that is likely to result from the open pits, waste rock facilities and waste rock backfilled from the open pits, tailings facilities, and heap leach facilities has been severely underestimated and in some cases neglected from consideration. 

 

As a result of these shortfalls in the reclamation plan relevant to acid drainage characteristics at the Phoenix Project site, the financial assurance provisions are significantly less than the amount that will most likely eventually be necessary to address reclamation and closure of the site.  Additional capital costs for improved cover designs and materials, and enhanced revegetation techniques will likely be necessary to accomplish source control.  Because of the pervasive and extensive nature of the acid drainage characteristics that the site characterization data soundly demonstrate, ground water remediation in the form of capture and treatment will likely be necessary for hundreds or even thousands of years (in perpetuity), and will require significantly greater difficulty and expense than has been suggested in the long-term contingent treatment plan.

 

As a rough estimate it would appear that the proposed reclamation plan is approximately 50% of what it correctly should be from a capital cost standpoint (or approximately $27M short), and from a water treatment and long-term operation and maintenance standpoint the proposed $1M surety amount is woefully inadequate compared to the $9-$47M estimated cost of water management in perpetuity.


 

 

 

 

 

Appendix

 

- References-

 

  1. Results of the Drilling Program and Laboratory Testing for the Zortman/Landusky Reclamation Project:  Draft Progress Report II (Subtask 4)
  2. Kuipers, J., Hardrock Mining Reclamation and Bonding Practices in the Western United States, National Wildife Federation, February 2001
  3. Record of Decision for Golden Sunlight Mine Permit Amendments 008 and 010, June 1998
  4. GSM Bond Calculation Sheets (attached in Appendix).  B.  Discharge Permit Molycorp Questa Mine
  5. DP-1055 Discharge Permit Molycorp Questa Mine
  6. DP-933 Discharge Permit Molycorp Questa Tailings Facility
  7.  Molycorp Questa Bond Calculation Sheets


[1] Phoenix Project Final Environmental Impact Statement, USDI Bureau of Land Management, Battle Mountain Field Office, Battle Mountain, NV, January 2002.

[2] Results of the Drilling Program and Laboratory Testing for the Zortman/Landusky Reclamation Project:  Draft Progress Report II (Subtask 4) demonstrated that the added alkalinity in the leach pads will eventually be consumed by sulfides and the leach pad material will become acid generating in 11 of 12 leach pads at the site (attached in Appendix).

[3] Section 8.0 Reclamation Cost Estimate, submitted as attachment to cover letter from A. Trippel, Newmont Mining Corporation to J. Sherve, BLM, March 2, 2001.

[4] Kuipers, J., Hardrock Mining Reclamation and Bonding Practices in the Western United States, National Wildife Federation, February 2001 (attached in Appendix).

[5] A. Record of Decision for Golden Sunlight Mine Permit Amendments 008 and 010, June 1998; GSM Bond Calculation Sheets (attached in Appendix).  B.  Discharge Permit Molycorp Questa Mine, DP
-1055; Discharge Permit Molycorp Questa Mine, DP-933; Molycorp Questa Bond Calculation Sheets (attached in Appendix).

[6] Final Supplemental Environmental Impact Statement for Reclamation of Zortman and Landusky Mines, Phillips County, Montana, Bureau of Land Management, State of Montana Department of Environmental Quality, December 2001.

[7] Handbook for Calculation of Reclamation Bond Amounts, Department of the Interior Office of Surface Mining, 2000.